Summary

Highly capable and motivated, with over 13 years of experience on design, implementation and engineering project management. Committed to technical excellency, innovation and compliance with the highest quality and safety standards. Proactive, organized and oriented toward results, with focus on client satisfaction achieving goals efficiently.

Developed skills in fast-paced engineering environment, focusing on problem-solving and project management. Transitioning to new field with strong background in analyzing data and optimizing processes. Looking to leverage these transferrable skills to drive success in new and challenging role.

Overview

15
15
years of professional experience
1
1
Language

Work History

Civil Engineer - Site Engineer - Project Manager

ASOCIACION ACCIDENTAL MICOLE
01.2023 - 01.2025
  • Project: "Mej De infraestructuras educativas de la red Cercado 1" (Improvement of Educational infrastructure for Cercado 1 Cluster)
  • Planning and implementation of construction-remodeling of 35 Educational centers
  • Negotiation with suppliers and planning of the logistics for the supply of materials in accordance to the works performed
  • Progress Sheet elaboration, monitoring of work Schedule and costs
  • Sales and promotion of the Building "Punta del Este" departments, achieving the closed deal of 12 departments sold out of 36

Civil Engineer/Project-Account Manager

CAPASI S.R.L
04.2019 - 12.2022
  • Managed contracts across multiple accounts, fostering seamless supplier and client relations.
  • Project Management of construction and/or remodeling projects
  • Personnel management, SOW, cost monitoring
  • Directed corrective and preventive maintenance projects for regional RBSs in Cochabamba.
  • Proyecto de mantenimiento correctivo y preventivo de Radio Bases Regional Cochabamba para el cliente final TELECEL S.A
  • Project "Ampliación de planta TEMPORAL" (Enlargement of the Temporal plant) in the city of Cochabamba for the final client TELECEL S.A

Civil Engineer/Site Engineer - Site Director

CO4 S.R.L
10.2017 - 04.2019
  • Planning and Construction implementation of RBSs for the Client ENTEL
  • Material procurement, supplier negotiation, work progress monitoring and report, QA/QC, progress sheet elaboration, personnel management
  • Material procurement, delivery coordination
  • New sites RBS_CBA_1011_Viscachani, RBS_CBA_1009_Llallagua-Totora, Technical: Structural Analisis, construction supervision, Project management in accordance to PMI lineouts
  • Deep understanding of BIM methodology for Project implementation

Civil Engineer/Site Engineer

EMPRESA CONSTRUCTORA TITANIUM S.R.L
05.2017 - 10.2017
  • Project: "CONSTRUCCIÓN DE 14 MULTIFAMILIARES EN EL MUNICIPIO DE COCHABAMBA CONDOMINIO LA TAMBORADA(BLOQUE 13 y 14)" (Construction of 14 multi family buildings in the municipality of Cochabamba La Tamborada Condominium (Block 13 and 14))
  • Supervised construction workforce while ensuring compliance with QA/QC standards.
  • Each block has 1 basement and 12 floors including level 0
  • Both buildings are reinforced concrete based structures and the main achievement is that at the peak of work we were able to cast 1 floor slab every 5 days

Civil Engineer - Civil Supervisor

SAMSUNG ENGINEERING Bolivia S.A.
05.2014 - 10.2015
  • Project: "Planta de Amoniaco y Urea" (Ammonia and Urea Production Plant)
  • Civil supervisor for civil works, mainly Main Substation, Urea Substation and Ammonia Substation
  • Negotiation with subcontractors and additionally planning the construction of administrative buildings, Urea bulk warehouse, fire station, admin substation
  • Revision of progress sheet, work Schedule and constant coordination with subcontractors and material suppliers

Civil Engineer/Site Engineer - Site Director

REMOC S.R.L
11.2013 - 04.2014
  • Construction Project implementation of RBSs for the final client ENTEL in PCC3 project
  • Site living during the implementation of the construction and tower assembly
  • New sites "Uyuni Nuevo" and "Pupusani" located in Uyuni, Potosi, Bolivia
  • New sites "Ironcollo","Fino", "Liriuni", "Cotapachi" in Cochabamba, Bolivia
  • New site "Oploca - Salo" in Tupiza, Potosi, Bolivia
  • Construction of concrete foundations for 42 meter high towers for the client FACER in community El Paso and Villa Esmeralda Sud in Cochabamba, Bolivia
  • Supervised construction progress on-site, addressing any discrepancies or issues promptly while maintaining safety protocols.

Civil Engineer/ Project Manager

HUAWEI Technologies (Bolivia) S.R.L
09.2011 - 02.2012
  • Planning and implementation of construction of RBSs for the client ENTEL in CCMPR II
  • Material logistics coordination from warehouse in La Paz
  • Santa Cruz
  • Site construction progress control, QC/QA coordination, subcontractor payment sheet elaboration
  • A total of 12 RBSs were built nationwide simultaneously
  • Monitored execution of contract work for compliance with design plans and specifications.
  • Supervised construction progress on-site, addressing any discrepancies or issues promptly while maintaining safety protocols.

Civil Engineer/ Regional Implementation Manager

HUAWEI del PERU SAC
03.2011 - 09.2011
  • Planning and implementation of civil works remodeling and telecom equipment installation for "TELEFONICA SWAP 2G/3G" project
  • Equipment requests from HQ to be shipped out to the country
  • Project progress control, QC/QA for the equipment installed, technical staff coordination
  • Project initially implemented in Lima and then Ica

Civil Engineer/ Regional Project Manager

HUAWEI Technologies (Bolivia) S.R.L
02.2010 - 03.2011
  • Planning and implementation of construction form Telecom RBS for the client ENTEL in TCT (Total Coverage Territory) project
  • Material logistics coordination from warehouse in La Paz
  • Santa Cruz
  • Site construction progress control, quality assurance, pay role and subcontractor payment control
  • New road opening, construction of concrete foundations under limited conditions
  • A total of 52 new RBSs were built and 2 additional towers were raised within an existing site
  • All these RBS were implemented simultaneously

Education

Civil Engineer - undefined

Universidad Mayor de San Simón
Cochabamba

Skills

MS - OFFICE Advanced

Software

Advanced, Intermediate, Advanced, Advanced, Intermediate, Advanced, High Intermediate, High Intermediate

Software

SQL

MS Visual Studio

Timeline

Civil Engineer - Site Engineer - Project Manager

ASOCIACION ACCIDENTAL MICOLE
01.2023 - 01.2025

Civil Engineer/Project-Account Manager

CAPASI S.R.L
04.2019 - 12.2022

Civil Engineer/Site Engineer - Site Director

CO4 S.R.L
10.2017 - 04.2019

Civil Engineer/Site Engineer

EMPRESA CONSTRUCTORA TITANIUM S.R.L
05.2017 - 10.2017

Civil Engineer - Civil Supervisor

SAMSUNG ENGINEERING Bolivia S.A.
05.2014 - 10.2015

Civil Engineer/Site Engineer - Site Director

REMOC S.R.L
11.2013 - 04.2014

Civil Engineer/ Project Manager

HUAWEI Technologies (Bolivia) S.R.L
09.2011 - 02.2012

Civil Engineer/ Regional Implementation Manager

HUAWEI del PERU SAC
03.2011 - 09.2011

Civil Engineer/ Regional Project Manager

HUAWEI Technologies (Bolivia) S.R.L
02.2010 - 03.2011

Civil Engineer - undefined

Universidad Mayor de San Simón
Gustavo A. Cano BurgoaCivil Engineer